Jul 14, 2016

Works ramp up on $51m Townsville utilities upgrade

Works ramp up on $51m Townsville utilities upgrade

Work on the first major package of Townsville’s four-year, $51 million CBD Utilities Upgrade project has begun.

Townsville City Council and head contractor BMD Constructions kicked off the works today on a section of Flinders St West between Blackwood and Fletcher streets.

Works in three other locations will commence over the next six weeks, including high-tech drilling under Ross Creek for the installation of a 400m section of new sewer main.

Water and Waste Committee chairman Paul Jacob said the upgrade of ageing water and sewerage pipelines was essential for future development.

“The CBD Utilities Upgrade is a city-building project that will increase the capacity of basic services to support the redevelopment of the inner-city and the target of 30,000 people working and living in the CBD by 2030,” Cr Jacob said.

Paul Jacob

Townsville City Council Water and Waste Committee chairman Paul Jacob.

“Upgrading water and sewerage mains, some up to 60 years old, will require significant excavations and the work is being done now to get these stages completed before the start of the wet season.

“Council’s major projects team has worked closely with BMD to package and stage works in a way that will minimise impacts on footpaths, parking and traffic flows as much as possible.

“Breaking the overall program down into smaller packages also maximises opportunities for local contractors.

“So far 96 per cent of the contract awarded to date has been to local suppliers and contractors and 52 out of the 53 inductions were for local workers.”

Council’s major projects manager Simon Ormes said the council had liaised with police, emergency services, taxis, Sunbus, and various agencies including Department of Transport and Main Roads, and utility companies on traffic management, access points, and continuity of services.

“With a project of this scope, keeping stakeholders and the public fully informed is extremely important. The project team is consulting residents and businesses in the CBD to address any issues as best they can and provide regular updates,” Mr Ormes said.

“We’re asking motorists to be patient with traffic changes, and to plan ahead and seek an alternative route where possible.”

Information on the CBD Utilities Upgrade and the latest package of works is available at https://www.townsville.qld.gov.au/building-planning-and-projects/council-projects/cbd-utilities-project

The upgrade began last year with early works in Stanley St from Flinders to Sturt streets, and the ongoing project in the old West Quarry to prepare the site for a future new water reservoir to supply the inner city area.

Local company Mendi Constructions won the contract for the West End quarry work.

Works to be completed between July and December includes:

  • Flinders St West.

Work started this week and will move progressively along Flinders St West between Blackwood and Fletcher St, starting at the Blackwood St intersection. Project duration 16 weeks.

  • Ross Creek underbore.

Work scheduled to start July 18 and continue for eight weeks. Drill rigs will be located in Archer St, South Townsville and the carpark of Enterprise House, south end of The Strand. 400m of 600mm pipework will be welded into one length and laid out along the footpath from Enterprise House past Anzac Park before being pulled under the creek in one continuous section. A section of the car park will be closed for the duration of the project.

  • Stanley St from Sturt St to Wills St

Main works to start in mid August and continue for 16 weeks.  Sturt St intersection will be closed for the first two weeks. The work will connect new pipework to underground services upgraded in Stanley St late last year between Flinders and Sturt. Work will progress further up Stanley Street in stages.

  • Sturt St

Work in Sturt Street between Stanley and Stokes streets will take approximately four months to complete and includes installation of new reticulation pipework for water supply to businesses and associated footpath replacements.

 

Recent Stories

Subscribe to IQ Now
Menu